ORGANIZATION
AMOUNT REQUESTED
$400,000
STATUS
None
OKLAHOMANS PROJECTED TO BENEFIT
0-25,000
ESTIMATED PROJECT DURATION
6-12 months
IMPACTED COUNTIES
Logan
PROJECT PURPOSE
The Town currently needs to make improvements to their wastewater lift station, collection system and wastewater lagoons. The lift station needs to be raised out of the flood plain, a drainage pipe has collapsed needs to be replaced along the lagoon dikes, Reshape and Rip Rap discharge area of the creek to eliminate erosion, an emergency standby generator, sewerlines and manholes.
EVIDENCE
Engineering Evaluation
POPULATION DESCRIPTION
This project will benefit the Town of Marshall. The Town was impacted by the pandemic due to reduced sales tax due to the lockdowns.
PERFORMANCE MEASURING
The Town will hire an approved engineering firm to take care of the design, bidding and construction management. They will also provide Resident Project Representative to monitor the contractor as the project proceeds. The Town will be presenting all the contracts and expenditures to the Council/Board for review and approval.
ONGOING INVESTMENT AMOUNT
$
ONGOING INVESTMENT DESCRIPTION
None
ONGOING INVESTMENT REQUIRED
Able to continue operation without additional funding from the State of Oklahoma
PROGRAM CATEGORY
Investments in Water, Sewer, and Broadband
PROGRAM SUBCATEGORY
Clean Water: Centralized Wastewater Collection and Conveyance
FEDERAL GRANT AMOUNT
$
FEDERAL GRANT DESCRIPTION
None
HQ COUNTY
Logan
ENTITY TYPE
Municipal government entity