ORGANIZATION
AMOUNT REQUESTED
$1,033,000
STATUS
None
OKLAHOMANS PROJECTED TO BENEFIT
0-25,000
ESTIMATED PROJECT DURATION
more than 24 months
IMPACTED COUNTIES
Muskogee
PROJECT PURPOSE
The Town/PWA is under a consent order with DEQ for DBP violations. The Town/PWA needs to install aa dedicated line to the tower and replace water line to ensure no more violations.
EVIDENCE
DEQ Consent Order
POPULATION DESCRIPTION
The community has experienced loss of lives, jobs, and funding.
PERFORMANCE MEASURING
The Town/PWA will hire an approved engineering firm to take care of design, bidding, construction management, and resident project representation. The Town/PWA will present all expenditures to the Council/Board for review and approval.
ONGOING INVESTMENT AMOUNT
$
ONGOING INVESTMENT DESCRIPTION
None
ONGOING INVESTMENT REQUIRED
Able to continue operation without additional funding from the State of Oklahoma
PROGRAM CATEGORY
Investments in Water, Sewer, and Broadband
PROGRAM SUBCATEGORY
Drinking water: Transmission & Distribution
FEDERAL GRANT AMOUNT
$